The metro line 4

 

[Fig. Metro Line 4]

-        Alignment: Thanh Xuan (district 12) – Ha Huy Giap – Nguyen Oanh – Nguyen Kiem – Phan Dinh Phung – Hai Ba Trung – Ben Thanh – Nguyen Thai Hoc – Ton Dan – Nguyen Huu Tho – Hiep Phuoc Urban area.

-         Total length: about 35.75 km (16.18 km underground and 17.77 km elevated).

-         Number of station: 32 stations (18 elevated stations and 14 underground stations).

-         Depot 1 at Thanh Xuan ward in district 12 with an area of 24.93 hectares.

-         Depot 2 at Hiep Phuoc ward in Nha Be district with an area of 21.28 hectares.

-         Expected investment form: ODA, PPP, …

-       Implementation progress: MAUR has submitted the Feasibility Study to HCMC’s PC for approval. Currently, Deparment of Transport is appraising the FS.