MONORAIL NO.2

[Fig. Monorail No.2]

-         Alignment: Highway No.50 – Nguyen Van Linh – Tran Nao – Xuan Thuy – Binh Quoi Urban area (Binh Thanh District).

-         Total length: 27.2 km.

-         Depot and workshop with an area of 10.1 ha at Phong Phu ward in Binh Chanh district;

-         Total investment cost (estimated): 715 million USD.

-       Expected investment form: ODA, PPP… (the project has been registered on the list of national projects calling for foreign investment to 2020 by Decision No. 631/QĐ-TTg dated April 29th , 2014)

-         Implementation progress: MAUR is preparing to conduct the Pre-Feasibility Study.

-         In the future, Monorail 2 will link to the metro line 3a.