TRAM WAY NO.1

[Fig. TRAMWAY No.1]

-         Alignment: Ba Son – Ton Duc Thang – Me Linh Roundabout – Vo Van Kiet – Ly Chieu Hoang – Western Bus Terminal.

-         Total length: 12.8 km (go on the ground).

-         Number of station: 6 stations and 17 stops.

-         Depot and workshop at Mien Tay Terminal with an area of 2.1 hectares.

-         Total investment cost (estimated): 250 million USD.

-         Expected investment form: ODA, PPP… (the project has been registered on the list of national projects calling for foreign investment to 2020 by Decision No. 631/QĐ-TTg dated April 29th , 2014)

-       Implementation progress: Currently, HCMC People's Committee has assigned the implementation of the bus rapid transit (BRT) project funded by World Bank to Department of Transportation during waiting for the investment of Tramway 1 project.